Shamrock Log Home Construction Day 1 - 14

This is a single story home 1664 sf. of heated space and features an 8ft. wide full length covered porch on the front including a 12ft. wide full length covered porch across the back.

Day 1 – 3

September 8th, Wednesday

Day 1 – Permits pulled at building department and scheduled footer inspection for tomorrow morning. All footers and pier pads dug out. Rebar installed and tied.

September 9th, Thursday

Day 2 – Received am footer inspection and passed. Poured all footers and pier pads.

September 10th, Friday

Day 3 – Scheduled Monday AM inspection for tie-beam and slab. Installed all block on crawlspace foundation including pier pads. Electricians onsite and set temporary electric pole for Monday’s inspection. 

Day_3_007__2__op_640x270.jpg
Day 3
Day_3_009__2__op_640x270.jpg
Day 3

Day 4

September 11th, Saturday

Day 4 – Cut out dirt and graded crawlspace to place 4″ slab after Mon. inspection. Finished placing rebar in tie-beam.

Shamrock__element278.jpg
Day 4
Day_3_009__2__op_640x270.jpg
Day 4

Day 5

September 12th, Sunday

Day 5 – Sprayed with the water truck and compacted to grade. Applied soil pest control treatment. Installed plastic sheathing to 4″ slab area. Ready for tomorrow’s AM inspection.

DSC01338__2__op_654x276.jpg
Day 5
DSC01344__2__op_654x276.jpg
Day 5
DSC01346__2__op_654x276.jpg
Day 5

Day 6

September 13th, Monday

Day 6 – 9:30 Inspection with Building Department on the slab, block cells, piers and tie- beam passed. Pumped concrete and filled block cells, piers, and tie-beams. Set all strapping and j-bolts. Poured 4″ slab inside of crawlspace.

DSC01348__2__op_654x276.jpg
Day 6
DSC01350__2__op_640x270.jpg
Day 6
DSC01351_op_640x426.jpg
Day 6

Day 7

September 14th, Tuesday

Day 7 – 1st-floor system materials and crew’s tool trailer delivered today.
Trimming tree branches overhanging home.

DSC01352__2__op_640x270.jpg
Day 7
DSC01355__2__op_640x270.jpg
Day 7

Day 8

September 15th, Wednesday

Day 8 – Crew onsite building floor system.

DSC01357__2__op_640x270.jpg
Day 8
DSC01358__2__op_640x270.jpg
Day 8
DSC01359__2__op_640x270.jpg
Day 8

Day 9

September 16th, Thursday

Day 9 – Crew completed floor system and ready for tomorrows AM inspection. Received covered porch materials.

DSC01360__2__op_640x314.jpg
Day 9
DSC01361__2__op_640x270.jpg
Day 9
DSC01363__2__op_640x270.jpg
Day 9

Day 10

September 17th, Friday

Day 10 – Waited till 1:30 for sub-floor framing inspection and release of temp. electric. Everything passed. Installed and completed sub-floor sheathing.

DSC01364__2__op_640x270.jpg
Day 10
DSC01365__2__op_640x270.jpg
Day 10
DSC01366__2__op_640x270.jpg
Day 10

Day 11

September 18th, Saturday

Day 11 – Worked on decks for front and back covered porches.

DSC01367__2__op_640x270.jpg
Day 11
DSC01368__2__op_640x270.jpg
Day 11

Day 12

September 19th, Sunday

Day 12 – No work today.

Day 13

September 20th, Monday

Day 13 – Installed decking to the front covered porch. Received forklift and unloaded two truckloads of logs and post materials. Organized placement of materials and started laying logs.

DSC01369__2__op_640x270.jpg
Day 13
DSC01370__2__op_640x270_op_640x270.jpg
Day 13
DSC01374__2__op_640x270.jpg
Day 13
DSC01372__2__op_640x270.jpg
Day 13

Day 14

September 21st, Tuesday

Day 14 – Crew stacking logs.

DSC01376__2__op_640x270.jpg
Day 14
DSC01377__2__op_640x270.jpg
Day 14